June 2023 Updates

  1. 6/26/23
  2. 6/19/23

Construction

Layout for the new fifth-floor duct work continued and the installation of the new duct got started. 

Floor leveling on the fifth floor was completed and looks good. 

Framing layout on the fourth and second floor was completed and the first  floor has very little left to complete. 

Electrical work in the parking garage continued with a couple of deliveries of material for the fifth floor.

Layout for electrical chases that run from the first to the fifth floor was started.

Demolition

HVAC demo in the second-floor fan is progressing well. 

Plumbing demo of the old restroom locations on second and fifth floors got started along with patching the plumbing penetrations.