Construction
Wall framing layout on the fifth floor is underway. Before that began, spray-on fire-resistant material was applied to the ironwork.

Electrical conduit work got started in the parking garage.
The first delivery of some of the new duct work for the fifth floor arrived.
Demolition
Various sections of ductwork throughout the building need to be demolished and rebuilt. The demolition work continues into this week.
The demolition of one of the air handlers in the second-floor fan room also began.
The interior entryway in the first-floor lobby was removed.

The air handler located on the fourth and fifth floors was also demoed.